Apapa trailer park ready April ending – FG

0
8

The Federal Controller of Works in Lagos, Mr Adedamola Kuti, on Friday said that the Apapa trailer park project in the state would be completed before the end of April.

Kuti told the News Agency of Nigeria (NAN) in Lagos that the shoreline protection aspect of the project was 25 per cent completed, adding that the entire project had achieved 94 per cent completion.

“We expect that the work will be completed this April and we should be handing the trailer park over to the NPA – Nigerian Port Authority – by end of this month.

“The materials we were waiting for have arrived and being cleared in the port as we speak.

“We have already completed 25 per cent of the shoreline protection which has been the major aspect holding us. The entire project is 94 per cent completed,” he told NAN.

Kuti said that facilities, including toilets and bathrooms, police post, ticketing section and boreholes to make the park comfortable for use, had been completed.